Soaring Costs: These 25 Public Infrastructure Projects Are Way Over Budget

brown wooden bridge over body of waterhttps://climate-crisis-247-bucket.nyc3.cdn.digitaloceanspaces.com/wp-content/uploads/2025/09/07201957/zjmkvh9pbrm-150x150.jpg

In an oversight hearing last week, Congressman Kevin Kiley called on FBI Director Kash Patel to formally investigate the project overrun costs of the California High-Speed Rail. According to Kiley, the cost of the high speed rail project has ballooned by more than $100 million over its original budget, becoming the costliest public infrastructure failure in the United States.

Hot property? From Maui to Malibu, These Affluent Enclaves Are Becoming Wildfire Hotspots
Whence the next pandemic? Cities Where the Next Pandemic Is Most Likely to Break Out

In the United States, at least a dozen public infrastructure projects have gone more than $1 billion over their original budgets in the last 25 years. Whether due to mismanagement, unrealistic cost estimates, expansions in scope, or delays in construction, these projects reflect the recurring challenges of bringing large-scale public works to completion on time and within budget, and are an impediment to transit infrastructure that can ease congestion and reduce harmful emissions. A look at the biggest project overruns of the last 25 years reveals the major public infrastructure failures of this century.

To determine the costliest public infrastructure overruns of the last 25 years, Climate Crisis 247 reviewed audits, budget reports, and press accounts of U.S. infrastructure projects from the Department of Transportation and other sources. Public work projects with clear, documented early cost estimates and later, final cost estimates were ranked based on the difference between first and last cost estimate. Early estimates are mostly based on federal Full Funding Grant Agreements, state ballot measures, and environmental review documents, while final costs are based on close-out audits for completed projects or the latest official estimates for those still underway. In instances where cost estimate ranges were provided, the higher estimates were used.

25. St. Louis Loop Trolley

Photo by Kenny Nguyá»…n on Unsplash

  • Estimated project overrun: $26.0 million
  • Initial project cost: $25.0 million (2010)
  • Final project cost: $51.0 million (2018)
  • Project details: 2.2-mile streetcar line in University City/Delmar Loop
 

24. Chicago Riverwalk Expansion

Photo by Gautam Krishnan on Unsplash

  • Estimated project overrun: $60.0 million
  • Initial project cost: $50.0 million (2012)
  • Final project cost: $110.0 million (2016)
  • Project details: Pedestrian riverfront project through downtown Chicago
 

23. Port of Miami Tunnel

Photo by Joe deSousa on Unsplash

  • Estimated project overrun: $61.0 million
  • Initial project cost: $607.0 million (2007)
  • Final project cost: $668.0 million (2014)
  • Project details: Twin highway tunnels linking Port of Miami to I-395
 

22. Austin Waller Creek Tunnel

Photo by Carlos Delgado on Unsplash

  • Estimated project overrun: $145.0 million
  • Initial project cost: $25.0 million (1998)
  • Final project cost: $170.0 million (2017)
  • Project details: Urban flood-control tunnel under downtown Austin
 

21. Seattle SR-99 Bertha Tunnel

Photo by Nitish Meena on Unsplash

  • Estimated project overrun: $200.0 million
  • Initial project cost: $3.1 billion (2009)
  • Final project cost: $3.3 billion (2019)
  • Project details: Highway tunnel replacement for Alaskan Way Viaduct
 

20. Washington Metro Silver Line Phase 2

Photo by Andy Feliciotti on Unsplash

  • Estimated project overrun: $270.0 million
  • Initial project cost: $2.8 billion (2012)
  • Final project cost: $3.1 billion (2022)
  • Project details: 11.4-mile extension to Dulles Airport and Loudoun County
 

19. San Francisco Central Subway

Photo by Hannibal Photography on Unsplash

  • Estimated project overrun: $372.0 million
  • Initial project cost: $1.6 billion (2013)
  • Final project cost: $2.0 billion (2022)
  • Project details: 1.7-mile subway connecting SoMa to Chinatown
 

18. Bayonne Bridge "Raise the Roadway" Project

Photo by Jocelyn Allen on Unsplash

  • Estimated project overrun: $400.0 million
  • Initial project cost: $1.3 billion (2010)
  • Final project cost: $1.7 billion (2017)
  • Project details: Raised bridge clearance for larger Panamax ships
 

17. Los Angeles Metro Regional Connector

Photo by Blake Lee on Unsplash

  • Estimated project overrun: $430.0 million
  • Initial project cost: $1.4 billion (2012)
  • Final project cost: $1.8 billion (2023)
  • Project details: 1.9-mile downtown LA light rail subway connector
 

16. Transbay Transit Center (Phase 1)

Photo by James Butterly on Unsplash

  • Estimated project overrun: $660.0 million
  • Initial project cost: $1.6 billion (2010)
  • Final project cost: $2.3 billion (2018)
  • Project details: Multimodal bus/rail transit hub in downtown SF
 

15. New Jersey Hudson-Bergen Light Rail Extension

Photo by Wyatte B on Unsplash

  • Estimated project overrun: $700.0 million
  • Initial project cost: $1.2 billion (2009)
  • Final project cost: $1.9 billion (2019)
  • Project details: Light rail extension south into Bayonne
 

14. New York Second Avenue Subway (Phase 1)

Photo by Luca Bravo on Unsplash

  • Estimated project overrun: $800.0 million
  • Initial project cost: $3.8 billion (2007)
  • Final project cost: $4.6 billion (2017)
  • Project details: 2-mile subway under Manhattan’s East Side
 

13. Federal Way Link Extension

Photo by Radek Kilijanek on Unsplash

  • Estimated project overrun: $996.0 million
  • Initial project cost: $2.2 billion (2017)
  • Final project cost: $3.2 billion (2019)
  • Project details: 7.8-mile Link light rail extension to Federal Way
 

12. Minneapolis Southwest LRT (Green Line Extension)

Photo by Nicole Geri on Unsplash

  • Estimated project overrun: $1.5 billion
  • Initial project cost: $1.3 billion (2011)
  • Final project cost: $2.8 billion (2025)
  • Project details: 14.5-mile LRT from Minneapolis to Eden Prairie
 

11. BART Transbay Core Capacity Program

Photo by NoName_13 on Pixabay

  • Estimated project overrun: $2.0 billion
  • Initial project cost: $2.4 billion (2017)
  • Final project cost: $4.4 billion (2023)
  • Project details: Capacity upgrades for BART Transbay corridor
 

10. The Portal Caltrain Downtown Extension (DTX)

Photo by derwiki on Pixabay

  • Estimated project overrun: $2.3 billion
  • Initial project cost: $6.0 billion (2018)
  • Final project cost: $8.3 billion (2023)
  • Project details: 1.3-mile rail link into Salesforce Transit Center
 

9. Denver International Airport Baggage System

Photo by David Syphers on Unsplash

  • Estimated project overrun: $2.8 billion
  • Initial project cost: $2.0 billion (1989)
  • Final project cost: $4.8 billion (1995)
  • Project details: Failed automated baggage handling system
 

8. Maryland Purple Line (Light Rail)

Photo by Cathy Poland on Unsplash

  • Estimated project overrun: $3.9 billion
  • Initial project cost: $5.6 billion (2016)
  • Final project cost: $9.5 billion (2024)
  • Project details: 16-mile light rail linking Bethesda to New Carrollton
 

7. Austin Project Connect (Initial Light Rail)

Photo by Justin Wallace on Unsplash

  • Estimated project overrun: $4.5 billion
  • Initial project cost: $5.8 billion (2020)
  • Final project cost: $10.3 billion (2025)
  • Project details: Scaled-back 9.8-mile light rail starter line
 

6. San Francisco-Oakland Bay Bridge Eastern Span

Photo by Looka Chow on Unsplash

  • Estimated project overrun: $5.4 billion
  • Initial project cost: $1.1 billion (1997)
  • Final project cost: $6.5 billion (2013)
  • Project details: Replacement of eastern span after earthquake damage
 

5. BART Silicon Valley Phase II

Photo by odya kun on Unsplash

  • Estimated project overrun: $5.8 billion
  • Initial project cost: $6.9 billion (2018)
  • Final project cost: $12.7 billion (2025)
  • Project details: 6-mile BART subway/extension through San Jose
 

4. Honolulu Skyline Rail

Photo by Spenser Sembrat on Unsplash

  • Estimated project overrun: $7.3 billion
  • Initial project cost: $5.1 billion (2012)
  • Final project cost: $12.4 billion (2023)
  • Project details: Elevated rapid transit line in Honolulu
 

3. New York East Side Access

Photo by David Vives on Unsplash

  • Estimated project overrun: $8.1 billion
  • Initial project cost: $3.5 billion (2000)
  • Final project cost: $11.6 billion (2023)
  • Project details: Rail connection bringing LIRR into Grand Central
 

2. Boston Big Dig

Photo by Osman Rana on Unsplash

  • Estimated project overrun: $19.2 billion
  • Initial project cost: $2.8 billion (1985)
  • Final project cost: $22.0 billion (2007)
  • Project details: Central artery/tunnel highway megaproject in Boston
 

1. California High-Speed Rail

Photo by Bruno Raffa on Unsplash

  • Estimated project overrun: $95.0 billion
  • Initial project cost: $33.0 billion (2008)
  • Final project cost: $128.0 billion (2025)
  • Project details: Planned high-speed rail line San Francisco to LA